The radiator configuration uses a RAL7035 paint coating system with a total dry film thickness of 260 μm for the project's marine high-corrosion environment requirements.
C5-M Marine Corrosion Protection
C5-M Marine Corrosion Protection
High-Temperature Cooling Configuration
Salt and Dust Environment Consideration
Overseas Project Delivery Coordination
Saudi Arabia · Red Sea Coastal Region
TengQi Technology supplied a project-specific panel radiator solution for the ACWA Al Mourjan (Rabigh 2) CCPP 01 combined-cycle power plant in Saudi Arabia. Designed for main transformer cooling system support, the scope addressed the combined challenges of high temperature, salt-laden marine air, humidity and dust in the Red Sea coastal environment.
ACWA Al Mourjan (Rabigh 2) CCPP 01 is a gas-fired combined-cycle power plant project located in the Rabigh coastal area of Saudi Arabia. In this operating context, the main transformer cooling system requires radiator equipment that can be coordinated with thermal duties while considering long-term exposure to a demanding coastal atmosphere.
Jiangsu Tengqi Electric Power Technology Co., Ltd., operating under the TengQi Technology (TQT) brand, provided transformer panel radiators as supporting equipment for the project’s main transformer cooling system. The supply scope concerned radiator manufacturing, corrosion-protection configuration and project delivery coordination; it did not include complete transformers or power plant equipment.
| Project Location | Rabigh, Saudi Arabia, Red Sea coastal region |
|---|---|
| Application | Combined-cycle power plant main transformer cooling system support |
| Radiator Model | PC3600-28/520 |
| Supply Quantity | 96 sets |
| Weight per Set | 891.8 kg |
| Natural Cooling Area | 66.65 m² per set |
| Forced-Air Cooling Area | 78.26 m² per set |
| Oil Weight | 347.1 kg per set |
| Coating System | Paint coating, RAL7035, total dry film thickness of 260 μm |
| Corrosion Protection Direction | C5-M marine high-corrosivity environment project support |
The listed configuration reflects the project input data. Final dimensions, interfaces, pressure requirements, test items, installation conditions and supply boundaries remain subject to approved drawings, technical agreements and order documents.
The Red Sea coastal climate presents a complex exposure profile for oil-immersed transformer radiators. A suitable solution needs to account for thermal requirements as well as the interaction of marine corrosion, elevated ambient temperature and airborne dust over the service period.
The PC3600-28/520 panel radiators were configured with a RAL7035 paint coating system and a total coating thickness of 260 μm for the project’s C5-M marine corrosion-protection direction. This approach is intended to provide enhanced resistance against moisture, salt mist and chloride-related corrosion risks associated with the Red Sea coastal environment. Effective corrosion protection also depends on surface preparation, coating continuity, treatment of welds and edges, shipping protection, installation practices and the acceptance requirements defined in project documentation.
The radiator configuration includes both natural cooling area and forced-air cooling area to support project-specific main transformer cooling requirements. Selection is based on coordination with relevant operating inputs, including transformer thermal load, ambient temperature, cooling arrangement and operational margin. The 66.65 m² natural cooling area and 78.26 m² forced-air cooling area per set provide the stated configuration basis for this supply.
For a coastal power plant where salt mist and dust may coexist, the radiator solution considered structural design, protective coating and manufacturing-delivery controls intended to reduce the risk of pollutant accumulation and corrosive-media ingress. Actual cleaning intervals, contamination levels and field operating performance depend on site exposure intensity, installation location, maintenance practices and operating conditions.
TengQi Technology supported the project through technical communication, product selection, manufacturing, quality verification, English documentation preparation, export packing and delivery coordination. Cooling-system control signals, monitoring signals and DCS interface requirements are subject to the equipment supply boundary, control-system configuration and final project technical agreement.
TengQi Technology is the brand of Jiangsu Tengqi Electric Power Technology Co., Ltd., a specialist manufacturer of transformer radiators and a provider of transformer cooling solutions. The company focuses on heat dissipation technology for large oil-immersed transformers and reactors, intelligent manufacturing of panel radiators, and related lifecycle service support.
For transformer manufacturers, EPC contractors, power companies and energy-sector customers, TengQi Technology can connect technical consultation, design support, product selection, sample development, batch manufacturing, quality verification, global delivery and after-sales technical support according to project needs. Its product range includes carbon steel, stainless steel and aluminum alloy panel radiator series.
Supported by manufacturing bases in Jiangsu and Zhejiang, together with a production and service base in Taiwan, TengQi Technology applies automated manufacturing, intelligent coating processes and quality-control practices to transformer radiator projects. Specific performance, inspection results, delivery schedules and service obligations for any project are determined by the applicable contract, approved drawings and technical documentation.
The Al Mourjan CCPP 01 radiator supply illustrates the combined requirements placed on transformer cooling components in a Red Sea coastal power plant: thermal-area coordination for main transformer cooling, C5-M-oriented marine corrosion protection, consideration of salt-and-dust exposure, and disciplined overseas project delivery support. Through the PC3600-28/520 configuration, 260 μm paint coating system and project-based coordination, TengQi Technology provided a practical panel radiator supply path for this demanding combined-cycle power plant environment.
Share your transformer parameters, cooling requirements or project conditions. TQT's engineering team will support product selection and customized solutions.